| Project | Cedar Lane Office Renovation · CL-01 | Date | October 16, 2026 |
|---|---|---|---|
| Location | Level 2, east wing | Prepared by | Demo Site Supervisor |
Clear, 16°C at 7:00 a.m. Interior work areas dry. East loading entrance open for deliveries.
| Crew / equipment | Quantity | Hours / activity |
|---|---|---|
| Framing crew | 3 workers | 7:00 a.m.–3:30 p.m.; 8 hours each, excluding lunch |
| Electrician | 1 worker | 8:00 a.m.–12:00 p.m.; rough-in coordination |
| Scissor lift | 1 unit | 3 operating hours; corridor ceiling work |
Installed 18 linear meters of metal stud partition on the east side of rooms 201–204. Door openings left ready for frame installation. Supervisor checked layout against drawing A-102 before framing began.
Received 40 gypsum boards at 9:10 a.m., ticket DEMO-104. Stored flat in the designated dry area. No visible delivery damage.
Room 204 ceiling framing paused from 10:00–11:00 a.m. while the electrician confirmed conduit clearance. Work resumed after clearance was marked. No injuries reported; housekeeping completed before departure.
CL01-101: east corridor before framing. CL01-102: stud layout at rooms 201–204. CL01-103: conduit clearance at room 204 before concealment.
Complete remaining corridor framing and start door frames. Confirm the revised frame delivery time with the supplier before 8:00 a.m.